Concept explainers
a)
To determine: Sequence of jobs based on decision rule First Come First Served (FCFS).
Introduction: First Come First Served is the
a)

Answer to Problem 19P
The sequence is A-B-C-D-E.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Due date |
A | 110 | 20 | 180 |
B | 120 | 30 | 200 |
C | 122 | 10 | 175 |
D | 125 | 16 | 230 |
E | 130 | 18 | 210 |
All the jobs are arrived on day 130.
Determine the sequence of the job using FCFS:
Job sequence | Processing time | Flow time | Due date | Start day | End day | Lateness |
A | 20 | 20 | 180 | 130 | 149 | |
B | 30 | 50 | 200 | 150 | 179 | |
C | 10 | 60 | 175 | 180 | 189 | 14 |
D | 16 | 76 | 230 | 190 | 205 | |
E | 18 | 94 | 210 | 206 | 223 | 13 |
Total | 94 | 300 | 27 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 130.
End day of Job A:
Jobs arrival rate is given as 130. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 149.
End day of Job B:
Start day of Job B is the next day of the end day of Job A. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 179.
End day of Job C:
Start day of Job C is the next day of the end day of Job B. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 189.
End day of Job D:
Start day of Job D is the next day of the end day of Job C. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 205.
End day of Job E:
Start day of Job E is the next day of the end day of Job D. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job E is 223.
Lateness of Job A, Job B, and Job D:
End day of Job A, Job B, and Job D is less than its respective due date. Hence, there would be no lateness.
Lateness of Job C:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job C is 14.
Lateness of Job E:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job E is 13.
b)
To determine: Sequence of jobs based on decision rule Earliest Due Date (EDD).
Introduction: Earliest Due Date is the scheduling rule, which helps to arrange the sequence in the order. Here, the job with the earliest due date would be served first. Then, the process would be going on from the earliest due date to the latest due date.
b)

Answer to Problem 19P
The sequence is C-A-B-E-D.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Due date |
A | 110 | 20 | 180 |
B | 120 | 30 | 200 |
C | 122 | 10 | 175 |
D | 125 | 16 | 230 |
E | 130 | 18 | 210 |
All the jobs are arrived on day 130.
Determine the sequence of the job using EDD:
Job sequence | Processing time | Flow time | Due date | Start day | End day | Lateness |
C | 10 | 10 | 175 | 130 | 139 | |
A | 20 | 30 | 180 | 140 | 159 | |
B | 30 | 60 | 200 | 160 | 189 | |
E | 18 | 78 | 210 | 190 | 207 | |
D | 16 | 94 | 230 | 208 | 223 | |
Total | 94 | 272 |
Working note:
Duration and due date for the jobs have been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 130. The job should be arranged based on due date. Due date should be assembled in the ascending order.
End day of Job C:
Jobs arrival rate is given as 130. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 139.
End day of Job A:
Start day of Job A is the next day of the end day of Job C. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 159.
End day of Job B:
Start day of Job B is the next day of the end day of Job A. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 189.
End day of Job E:
Start day of Job E is the next day of the end day of Job B. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job E is 207.
End day of Job D:
Start day of Job D is the next day of the end day of Job E. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 223.
Lateness of Job A, Job B, Job C, Job D, and Job E:
End day of all the jobs is less than its respective due date. Hence, there would be no lateness.
c)
To determine: Sequence of jobs based on decision rule Shortest Processing Time (SPT).
Introduction: Shortest Processing Tine is the scheduling rule which helps to arrange the sequence in the order. Here, the job with the shortest duration would be served first. Then, the process would be going on from shortest to largest duration.
c)

Answer to Problem 19P
The sequence is C-D-E-A-B.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Due date |
A | 110 | 20 | 180 |
B | 120 | 30 | 200 |
C | 122 | 10 | 175 |
D | 125 | 16 | 230 |
E | 130 | 18 | 210 |
All the jobs are arrived on day 130.
Determine the sequence of the job using SPT:
Job sequence | Processing time | Flow time | Due date | Start day | End day | Lateness |
C | 10 | 10 | 175 | 130 | 139 | |
D | 16 | 26 | 230 | 140 | 155 | |
E | 18 | 44 | 210 | 156 | 173 | |
A | 20 | 64 | 180 | 174 | 193 | 13 |
B | 30 | 94 | 200 | 194 | 223 | 23 |
Total | 94 | 238 | 36 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 130. The job should be arranged based on the duration (processing time). The duration should be assembled in the ascending order.
End day of Job C:
Jobs arrival rate is given as 130. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 139.
End day of Job D:
Start day of Job D is the next day of the end day of Job C. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 155.
End day of Job E:
Start day of Job E is the next day of the end day of Job D. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job E is 173.
End day of Job A:
Start day of Job A is the next day of the end day of Job E. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 193.
End day of Job B:
Start day of Job B is the next day of the end day of Job A. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 223.
Lateness of Job C, Job D, and Job E:
End day of Job C, Job D, and Job E are less than its respective due date. Hence, there would be no lateness.
Lateness of Job A:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job A is 13.
Lateness of Job B:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job B is 23.
d)
To determine: Sequence of jobs based on decision rule Longest Processing Time (LPT).
Introduction: Largest Processing Tine is the scheduling rule, which helps to arrange the sequence in the order. Here, the job with the largest duration would be served first. Then, the process would be going on from largest to shortest duration.
d)

Answer to Problem 19P
The sequence is B-A-E-D-C.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Due date |
A | 110 | 20 | 180 |
B | 120 | 30 | 200 |
C | 122 | 10 | 175 |
D | 125 | 16 | 230 |
E | 130 | 18 | 210 |
All the jobs are arrived on day 130.
Determine the sequence of the job using LPT:
Job sequence | Processing time | Flow time | Due date | Start day | End day | Lateness |
B | 30 | 30 | 200 | 130 | 159 | |
A | 20 | 50 | 180 | 160 | 179 | |
E | 18 | 68 | 210 | 180 | 197 | |
D | 16 | 84 | 230 | 198 | 213 | |
C | 10 | 94 | 175 | 214 | 223 | 48 |
Total | 94 | 326 | 48 |
Working note:
Duration and due date for the jobs have been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 130. The job should be arranged based on the duration (processing time). The duration should be assembled in the descending order
End day of Job B:
Jobs arrival rate is given as 130. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job B is 159.
End day of Job A:
Start day of Job A is the next day of the end day of Job B. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job A is 179.
End day of Job E:
Start day of Job E is the next day of the end day of Job A. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job E is 197.
End day of Job D:
Start day of Job D is the next day of the end day of Job E. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job D is 213.
End day of Job C:
Start day of Job C is the next day of the end day of Job D. End day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the end day of Job C is 223.
Lateness of Job B, Job A, Job E, and Job D:
End day of Job B, Job A, Job E, and Job D are less than its respective due date. Hence, there would be no lateness.
Lateness of Job C:
It is calculated by subtracting the end day of the job from the due date of the project. Hence, the lateness of Job C is 48.
Summary:
Scheduling rule | Average lateness | Average flow time | Average number of jobs in system |
FCFS | 5.4 | 60.0 | 3.2 |
EDD | 0.0 | 54.4 | 2.9 |
SPT | 7.2 | 47.6 | 2.5 |
LPT | 9.6 | 65.2 | 3.5 |
First Come First Served (FCFS):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 5.4.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 60.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 3.2.
Earliest Due Date (EDD):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 0.0.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 54.4.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.9.
Shortest Processing Time (SPT):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 7.2.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 47.6.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.5.
Longest Processing Time (LPT):
Average tardiness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 9.6.
Average flow time:
It is calculated by dividing the total flow time with the number of jobs. Hence, the average flow time is 65.2.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 3.55.
Hence, Earliest Due Date is the best method for the average lateness. Shortest processing time has the minimum average flow time and average number of jobs in systems.
Want to see more full solutions like this?
Chapter 15 Solutions
Principles Of Operations Management
- 1. Hofstede’s Cultural Dimensions in Managerial Decision-MakingChoose two of Hofstede’s dimensions (e.g., Power Distance, Individualism–Collectivism, Uncertainty Avoidance, Masculinity–Femininity) and analyze how differences between two specific countries impact managerial decisions such as delegation, risk-taking, or performance appraisal. Provide real or hypothetical business scenarios that illustrate these effects. 2. Communication Styles Across CulturesCompare and contrast high-context versus low-contextcommunication cultures (Hall’s framework). Select one high-context country and one low-context country and evaluate the implications for written reports, virtual meetings, and feedback delivery. Develop three practical guidelines for an international manager to navigate these differences effectively.arrow_forwardCalculate the Current Ratio for Home Depot for the fiscal year-end February 2019? Enter the response as a ratio, rounded to two decimal places (X.XX) Calculate the Debt to Equity Ratiof or Home Depot for the fiscal year-end February 2019. Enter the response as a ratio, rounded to two decimal places (X.XX) Calculate the Rate of Return on Total Assets for Home Depot for the fiscal year-end February 2019. Round your answer to two decimal places For disclosure purposes, how many segments did the company report?arrow_forwardDiscuss Probability and Probability Distributions, Provide good rationale and share some examples.arrow_forward
- 3. Conducting Research:What types of information should a negotiator research before entering a negotiation? Provide an example of how effective research can strengthen a negotiator’s position. 4. Anticipating the Other Party’s Interests:Why is it important to understand the interests and objectives of the other party? How can this knowledge improve the chances of a successful negotiation? 5. Chapter Summary Reflection:Reflect on the key lessons from Chapter 3. How do preparation and research work together to build confidence and increase your negotiation effectiveness?arrow_forwardUse real-life or hypothetical examples where appropriate to support your responses. 1. Preparation and Planning:Why is preparation and planning considered essential for negotiation success? Describe at least two steps negotiators should take during the planning phase. 2. Setting Goals and Priorities:When preparing for a negotiation, how should a negotiator set their goals and determine their priorities? How do clear goals impact the negotiation outcome?arrow_forwardWhat was the closing stock price on the last day of business for the fiscal year-end February 2019 for Home Depot? Look it up. Enter the response in terms of dollars and cents Calculate the Price/Earnings ratio at the end of the fiscal year-end February 2019 for Home Depot. Round your answer to two decimal places. Enter as (XX.XX) How many shares of Treasury Stock does the Home Depot have at their fiscal year-end February 2019? If none, enter “0”. Did the Home Depot pay dividends? What is the amount per share for the entire fiscal year-end Februaruy 2019? If none, enter “0”. Enter the response in terms of dollars and cents ($XXX.XX)arrow_forward
- What were the Basic Earnings Per Share for the fiscal year-end February 2019 for Home Depot published in the financial statements? Enter the response in terms of dollars and cents ($XXX.XX)arrow_forwardCalculate the Current Ratio for Home Depot for the fiscal year-end February 2019? Enter the response as a ratio, rounded to two decimal places (X.XX) Calculate the Debt to Equity Ratiof or Home Depot for the fiscal year-end February 2019. Enter the response as a ratio, rounded to two decimal places (X.XX) Calculate the Rate of Return on Total Assets for Home Depot for the fiscal year-end February 2019. Round your answer to two decimal places For disclosure purposes, how many segments did the company report?arrow_forwardWhat was the closing stock price on the last day of business for the fiscal year-end February 2019 for Home Depot? Look it up. Enter the response in terms of dollars and cents ($XXX.XX) Calculate the Price/Earnings ratio at the end of the fiscal year-end February 2019?.Round your answer to two decimal places. Enter as (XX.XX) How many shares of Treasury Stock does the company have at their fiscal year-end February 2019? If none, enter “0”. Did the company pay dividends? What is the amount per share for the entire fiscal year-end February 2019? If none, enter “0”. Enter the response in terms of dollars and cents ($XXX.XX) What is the amount of cash generated (or used) by Operating Activities on the Statement of Cash Flows for the fiscal year-end February 2019 ? (Enter the response in terms of dollars ($XXX,XXX,XXX,XXX or (-$XXX,XXX,XXX,XXX)) Calculate the Gross Profit Ratio for the fiscal year-end February 2019.Round your answer to two decimal places. Enter the response in terms of…arrow_forward
- What is the name of the Auditing Firm that conducted the audit for Home Depot for the fiscal year-end February 2019? What is the fiscal year-end date for the financials? State the answer in this format: MMDD19 What inventory method does the company use for the majority of their merchandise inventory? What depreciation method(s) are used to prepare the financial statements? Select all that apply. List the useful lives of the fixed assets used to calculate depreciation. Select all that apply. What were the number of common shares outstanding on the last day of the fiscal year? State the answer in the following format: (XXX,XXX,XXX) (not in millions)…arrow_forwardWalmart is one of the most important supermarket chains in the United States. It has subsidiaries in over 25 countries, with more than 6,000 stores. In 2014, however, it had problems in China. Based on the contents of the units, and any secondary sources that you consider relevant (such as articles published online or in another format), answer the following questions, providing support for your answers. Why did Walmart’s internationalization in China fail? What was the strategic option for entering the Chinese market? What would you have recommended? Which groups of stakeholders were not taken into consideration? What would the correct stakeholder analysis have been?arrow_forwarddescribe a company you believe uses these 3 items.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Foundations of Business (MindTap Course List)MarketingISBN:9781337386920Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage LearningFoundations of Business - Standalone book (MindTa...MarketingISBN:9781285193946Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage Learning