To determine: Thejob sequence, flow time, utilization metric, average number of jobs, and average lateness for EDD, SPT, LPT, and FCFS.
Introduction:
a)

Answer to Problem 18P
The values in the given table have been computed.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Date order due |
BR-02 | 228 | 15 | 300 |
CX-01 | 225 | 25 | 270 |
DE-06 | 230 | 35 | 320 |
RG-05 | 235 | 40 | 360 |
SY-11 | 231 | 30 | 310 |
All the jobs are arrived on day 241.
Table to compute:
Dispatching rule | Job sequence | Flow time | Utilization rating | Average number of jobs | Average lateness |
EDD | |||||
SPT | |||||
LPT | |||||
FCFS |
Computed table:
Dispatching rule | Job sequence | Flow time | Utilization rating | Average number of jobs | Average lateness |
EDD | CX-BR-SY-DE-RG | 385 | 37.60% | 2.66 | 10 |
SPT | BR-CX-SY-DE-RG | 375 | 38.60% | 2.59 | 12 |
LPT | RG-DE-SY-CX-BR | 495 | 29.30% | 3.41 | 44 |
FCFS | CX-BR-DE-SY-RG | 390 | 37.20% | 2.69 | 12 |
Supporting calculation:
Determine the sequence of the job using FCFS:
Processing time | Due date | Flow time | Completion time | Late | |
BR-02 | 15 | 300 | 15 | 265 | 0 |
CX-01 | 25 | 270 | 40 | 280 | 0 |
DE-06 | 35 | 320 | 75 | 315 | 0 |
RG-05 | 40 | 360 | 115 | 345 | 35 |
SY-11 | 30 | 310 | 145 | 385 | 25 |
Total | 390 | 60 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 241.
First Come First Served (FCFS):
Completion day of CX-01:
Jobs arrival rate is given as 241. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 265.
Completion day of BR-02:
Start day of BR-02 is the next day of the completion day of CX-01. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 280.
Completion day of DE-06:
Start day of DE-06 is the next day of the completion day of BR-02. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day of DE-06 is 315.
Completion day of SY-11:
Start day of SY-11 is the next day of the completion day of DE-06. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day of SY-11 is 345.
Completion day of RG-05:
Start day of RG-05 is the next day of the completion day of SY-11. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day of RG-05 is 385.
Lateness of CX-01, BR-02, and DE-06:
Completion day of CX-01, BR-02, and DE-06 is less than its respective due date. Hence, there would be no lateness.
Lateness of SY-11:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 35.
Lateness of RG-05:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 25.
Determine the sequence of the job using SPT:
Processing time | Due date | Flow time | Completion time | Late | |
BR-02 | 15 | 300 | 15 | 255 | 0 |
CX-01 | 25 | 270 | 40 | 280 | 10 |
SY-11 | 30 | 310 | 70 | 310 | 0 |
DE-06 | 35 | 320 | 105 | 345 | 25 |
RG-05 | 40 | 360 | 145 | 385 | 25 |
Total | 375 | 60 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 241.
Shortest Processing Time (SPT):
Completion day of BR-02:
Jobs arrival rate is given as 241. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 255.
Completion day of CX-01:
Start day of CX-01 is the next day of the completion day of BR-02. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 280.
Completion day of SY-11:
Start day of SY-11 is the next day of the completion day of CX-01. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 310.
Completion day of DE-06:
Start day of DE-06 is the next day of the completion day of SY-11. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 345.
Completion day of RG-05:
Start day of RG-05 is the next day of the completion day of DE-06. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 385.
Lateness of BR-02 and SY-11:
Completion day of BR-02 and SY-11 is less than its respective due date. Hence, there would be no lateness.
Lateness of CX-01:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 10.
Lateness of DE-06:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 25.
Lateness of RG-05:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 25.
Determine the sequence of the job using LPT:
Processing time | Due date | Flow time | Completion time | Late | |
RG-05 | 40 | 360 | 40 | 280 | 0 |
DE-06 | 35 | 320 | 75 | 315 | 0 |
SY-11 | 30 | 310 | 105 | 345 | 35 |
CX-01 | 25 | 270 | 130 | 370 | 100 |
BR-02 | 15 | 300 | 145 | 385 | 85 |
Total | 495 | 220 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 241.
Largest Processing Time (LPT):
Completion day of RG-05:
Jobs arrival rate is given as 241. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 280.
Completion day of DE-06:
Start day of DE-06 is the next day of the completion day of RG-05. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 315.
Completion day of SY-11:
Start day of SY-11 is the next day of the completion day of DE-06. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 345.
Completion day of CX-01:
Start day of CX-01 is the next day of the completion day of SY-11. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 370.
Completion day of BR-02:
Start day of BR-02 is the next day of the completion day of CX-01. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 385.
Lateness of RG-05 and DE-06:
Completion day of RG-05 and DE-06 is less than its respective due date. Hence, there would be no lateness.
Lateness of SY-11:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 35.
Lateness of CX-01:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 100.
Lateness of BR-02:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 85.
Determine the sequence of the job using EDD:
Processing time | Due date | Flow time | Completion time | Late | |
CX-01 | 25 | 270 | 25 | 265 | 0 |
BR-02 | 15 | 300 | 40 | 280 | 0 |
SY-11 | 30 | 310 | 70 | 310 | 0 |
DE-06 | 35 | 320 | 105 | 345 | 25 |
RG-05 | 40 | 360 | 145 | 385 | 25 |
Total | 385 | 50 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 241.
Earliest Due Date (EDD):
Completion day of CX-01:
Jobs arrival rate is given as 241. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 265.
Completion day of BR-02:
Start day of BR-02 is the next day of the completion day of CX-01. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 280.
Completion day of SY-11:
Start day of SY-11 is the next day of the completion day of DE-06. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day of SY-11 is 310.
Completion day of DE-06:
Start day of DE-06 is the next day of the completion day of BR-02. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day of DE-06 is 345.
Completion day of RG-05:
Start day of RG-05 is the next day of the completion day of SY-11. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day of RG-05 is 385.
Lateness of CX-01, BR-02, and SY-11:
Completion day of CX-01, BR-02, and SY-11 is less than its respective due date. Hence, there would be no lateness.
Lateness of DE-06:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 25.
Lateness of RG-05:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 25.
Summary:
Dispatching rule | Job sequence | Flow time | Utilization rating | Average number of jobs | Average lateness |
EDD | CX-BR-SY-DE-RG | 385 | 37.60% | 2.66 | 10 |
SPT | BR-CX-SY-DE-RG | 375 | 38.60% | 2.59 | 12 |
LPT | RG-DE-SY-CX-BR | 495 | 29.30% | 3.41 | 44 |
FCFS | CX-BR-DE-SY-RG | 390 | 37.20% | 2.69 | 12 |
Working note:
Job sequence and flow time have been calculated in the above segments.
Earliest Due Date (EDD):
Average lateness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 10.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.66.
Utilization rating:
It is calculated by dividing total processing time and total flow time. Hence, the utilization rating is 38.6%.
Shortest Processing Time (SPT):
Average lateness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 12.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.59.
Utilization rating:
It is calculated by dividing total processing time and total flow time. Hence, the utilization rating is 38.6%.
Largest Processing Time (LPT):
Average lateness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 44.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 3.41.
Utilization rating:
It is calculated by dividing total processing time and total flow time. Hence, the utilization rating is 29.3%.
First Come First Served (FCFS):
Average lateness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 44.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.69.
Utilization rating:
It is calculated by dividing total processing time and total flow time. Hence, the utilization rating is 37.2%.
b)
To determine: The dispatching rule that has the best score in flow time.
Introduction: Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan on allocating human resources and machinery.
b)

Answer to Problem 18P
Shortest Processing Time has the best flow time.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Date order due |
BR-02 | 228 | 15 | 300 |
CX-01 | 225 | 25 | 270 |
DE-06 | 230 | 35 | 320 |
RG-05 | 235 | 40 | 360 |
SY-11 | 231 | 30 | 310 |
Best score in flow time:
Dispatching rule | Job sequence | Flow time | Utilization rating | Average number of jobs | Average lateness |
EDD | CX-BR-SY-DE-RG | 385 | 37.60% | 2.66 | 10 |
SPT | BR-CX-SY-DE-RG | 375 | 38.60% | 2.59 | 12 |
LPT | RG-DE-SY-CX-BR | 495 | 29.30% | 3.41 | 44 |
FCFS | CX-BR-DE-SY-RG | 390 | 37.20% | 2.69 | 12 |
According to the above table, Shortest Processing Time (SPT) has the best score in flow time. It has less flow time when compare to EDD, LPT, and FCFS.
Hence, SPT has the best score in flow time.
c)
To determine: The dispatching rule that has the best score in utilization metric.
Introduction: Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan on allocating human resources and machinery.
c)

Answer to Problem 18P
Shortest Processing Time has the best utilization metric.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Date order due |
BR-02 | 228 | 15 | 300 |
CX-01 | 225 | 25 | 270 |
DE-06 | 230 | 35 | 320 |
RG-05 | 235 | 40 | 360 |
SY-11 | 231 | 30 | 310 |
Best score in utilization metric:
Dispatching rule | Job sequence | Flow time | Utilization rating | Average number of jobs | Average lateness |
EDD | CX-BR-SY-DE-RG | 385 | 37.60% | 2.66 | 10 |
SPT | BR-CX-SY-DE-RG | 375 | 38.60% | 2.59 | 12 |
LPT | RG-DE-SY-CX-BR | 495 | 29.30% | 3.41 | 44 |
FCFS | CX-BR-DE-SY-RG | 390 | 37.20% | 2.69 | 12 |
According to the above table, Shortest Processing Time (SPT) has the best score in utilization metric. It has maximum utilization metric when compare to EDD, LPT, and FCFS.
Hence, SPT has the best score in utilization metric.
d)
To determine: The dispatching rule that has the best score in average lateness.
Introduction: Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan allocating human resources and machinery.
d)

Answer to Problem 18P
Earliest Due Date has the best utilization metric.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Date order due |
BR-02 | 228 | 15 | 300 |
CX-01 | 225 | 25 | 270 |
DE-06 | 230 | 35 | 320 |
RG-05 | 235 | 40 | 360 |
SY-11 | 231 | 30 | 310 |
Best score in average lateness:
Dispatching rule | Job sequence | Flow time | Utilization rating | Average number of jobs | Average lateness |
EDD | CX-BR-SY-DE-RG | 385 | 37.60% | 2.66 | 10 |
SPT | BR-CX-SY-DE-RG | 375 | 38.60% | 2.59 | 12 |
LPT | RG-DE-SY-CX-BR | 495 | 29.30% | 3.41 | 44 |
FCFS | CX-BR-DE-SY-RG | 390 | 37.20% | 2.69 | 12 |
According to the above table, Earliest Due Date (EDD) has the best score in average lateness. It has less average lateness when compare to SPT, LPT, and FCFS.
Hence, EDD has the best score in average lateness.
e)
To determine: The dispatching rule that would be selected by Person X.
Introduction: Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan allocating human resources and machinery.
e)

Answer to Problem 18P
Person X would select Earliest Due Date.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Date order due |
BR-02 | 228 | 15 | 300 |
CX-01 | 225 | 25 | 270 |
DE-06 | 230 | 35 | 320 |
RG-05 | 235 | 40 | 360 |
SY-11 | 231 | 30 | 310 |
Best score in average lateness:
Dispatching rule | Job sequence | Flow time | Utilization rating | Average number of jobs | Average lateness |
EDD | CX-BR-SY-DE-RG | 385 | 37.60% | 2.66 | 10 |
SPT | BR-CX-SY-DE-RG | 375 | 38.60% | 2.59 | 12 |
LPT | RG-DE-SY-CX-BR | 495 | 29.30% | 3.41 | 44 |
FCFS | CX-BR-DE-SY-RG | 390 | 37.20% | 2.69 | 12 |
According to the above table, EDD has the less average lateness and other values are also having a slight difference when compared with SPT. Thus, EDD should be selected.
Hence, Person X would choose Earliest Due Date (EDD).
Want to see more full solutions like this?
Chapter 15 Solutions
Principles Of Operations Management
- For the duration of this course, you will be the Chief Data Officer (CDO) of a fictional firm of your choice. You have a data enterprise that contains structured and unstructured data As the CDO, what did you decide to build, a data warehouse or a data lake? Would you build both? Why? If you only select building one platform, you must justify the decision. I want to know the benefits and tradeoffs of that decisionarrow_forwardNavigating clinical coding, billing, and insurance verification is crucial in healthcare. These elements not only affect healthcare providers' compensation but also shape a patient's access to treatments. Through discussion and role-play, let's apply our knowledge to a real-world scenario. For your initial post, answer the following questions: 1. Define the terms "insurance verification" and "benefit determination" using proper clinical coding and billing terminology. Why is it essential to verify a patient's insurance coverage prior to an office visit? 2. Scenario: Imagine you are at the front desk of a healthcare facility. The previous day, you verified the insurance status for all patients scheduled for the upcoming day and received confirmation of their active status. However, when the first patient of the day arrives for their 9am appointment, a subsequent eligibility check shows their insurance is now inactive. a. Describe the immediate steps you would take in response to this…arrow_forwardWhat is the obstacle that the mental load involves, the ongoing cognitive involvement that is required to maintain things functioning properly? What are the advantages and disadvantages of maintaining the mental load so that things function properly? What are the mental boundaries that continue role-switch depletes mental and emotional reserves, resulting in heightened stress, diminished life satisfaction, and emotional tiredness?arrow_forward
- To start, consider a time when miscommunication led to a problem in your professional or personal life. Share a personal experience where miscommunication led to a problem. Analyze the situation using a communication model (e.g., Shannon-Weaver, Transactional Model) to identify the breakdown in the communication process. What could have been done differently to prevent the miscommunication?arrow_forwardWhat is the household mental load? And how does it work? How is planning a dinner essential to the family? How are the cognitive and emotional burdens often paired with managing multiple responsibilities at home and in the workplace? How does handling professional commitments and personal well-being, a mental load, overwhelm a person, leading to stress and depletion?arrow_forwardWhat are the household chores, and how do we explore the numerous benefits of sharing? How can improving relationships enhance the quality of life? By sharing household responsibilities, we can turn routine tasks into opportunities for connection and collaboration. How to focus on how to strengthen relationships, boost efficiency, and enhance overall well-being in the family? What are the obstacles to checking the security of the house, making sure groceries are stocked, or attending to sick family members?arrow_forward
- 2. New Trade Theory and Market Structure a. Summarize how new trade theory accounts for economies of scale and first-mover advantages, in contrast to classical theories. b. Choose an industry—such as commercial aircraft, consumer electronics, or academic publishing—where a few large firms dominate. c. Critically evaluate how first-mover advantages and scale economies impact global competition and trade flows in your chosen industry. 3. Trade Policy Instruments and Their Business Impact a. Identify and describe at least three trade policy instruments (e.g. tariffs, quotas, export subsidies, local-content requirements, standards). b. Pick a country that has implemented a recent trade policy change (for instance: increased tariffs, stricter import standards, or incentives for domestic production). c. Analyze how this policy change affects both local and international businesses using the frameworks from the chapter. Then, propose two strategic responses a multinational firm…arrow_forwarddescribe how you would fix or correct these culture issues.arrow_forward1. Hofstede’s Cultural Dimensions in Managerial Decision-MakingChoose two of Hofstede’s dimensions (e.g., Power Distance, Individualism–Collectivism, Uncertainty Avoidance, Masculinity–Femininity) and analyze how differences between two specific countries impact managerial decisions such as delegation, risk-taking, or performance appraisal. Provide real or hypothetical business scenarios that illustrate these effects. 2. Communication Styles Across CulturesCompare and contrast high-context versus low-contextcommunication cultures (Hall’s framework). Select one high-context country and one low-context country and evaluate the implications for written reports, virtual meetings, and feedback delivery. Develop three practical guidelines for an international manager to navigate these differences effectively.arrow_forward
- Calculate the Current Ratio for Home Depot for the fiscal year-end February 2019? Enter the response as a ratio, rounded to two decimal places (X.XX) Calculate the Debt to Equity Ratiof or Home Depot for the fiscal year-end February 2019. Enter the response as a ratio, rounded to two decimal places (X.XX) Calculate the Rate of Return on Total Assets for Home Depot for the fiscal year-end February 2019. Round your answer to two decimal places For disclosure purposes, how many segments did the company report?arrow_forwardDiscuss Probability and Probability Distributions, Provide good rationale and share some examples.arrow_forward3. Conducting Research:What types of information should a negotiator research before entering a negotiation? Provide an example of how effective research can strengthen a negotiator’s position. 4. Anticipating the Other Party’s Interests:Why is it important to understand the interests and objectives of the other party? How can this knowledge improve the chances of a successful negotiation? 5. Chapter Summary Reflection:Reflect on the key lessons from Chapter 3. How do preparation and research work together to build confidence and increase your negotiation effectiveness?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Foundations of Business (MindTap Course List)MarketingISBN:9781337386920Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage LearningFoundations of Business - Standalone book (MindTa...MarketingISBN:9781285193946Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage Learning