Project | Probable Date of Completion (PDC) as of February 2014 | Cost | ||
---|---|---|---|---|
Original | Revised | Original | Revised | |
Light Combat Aircraft (LCA), Phase-II | December 2008 | December 2015 | Rs.3301.75 Cr | Rs.5777.53 Cr |
Naval Light Combat Aircraft (LCA, Navy), Phase-I | March 2010 | December 2014 | Rs.948.90 Cr | Rs.1714.98 Cr |
Aero-engine Kaveri | December 1996 | December 2009 # | Rs.383.81 Cr | Rs.2839.00 Cr |
Airborne Early Warning & Control (AEW&C) System | October 2011 | March 2014 | Rs.1800.00 Cr | Rs.2157.00 Cr |
Long Range Surface-to-Air Missile (LR-SAM) | May 2011 | December 2015 | Rs.2606.02 Cr | No revision. |
Air-to-Air Missile, Astra | August 2012 | December 2016 | ||
# PDC was further extended within the sanctioned cost and scope. |