Sl. No. |
Description of the Work |
Name and Address of
the Employer |
Contract No. and date |
Date of award of work |
Stipulated date of
completion |
Value of work as per
order
( Rs. in lacs) |
Remarks |
1 |
Construction of Town
Hall at Sonamura, West Tripura |
Executive Director
RBG Head-Tripura
NBCC
NBCC Bhawan, Lodhi Road,
New Delhi - 110003
|
NBCC/ED/RBG/ AGT/LOI/2012/864 Dt. 14.05.2012 |
14.05.2012 |
Nov-13 |
2064.53 |
Completion Period
18 Months |
2 |
Construction of
Water Supply System for Upper Shilong Water Supply Project under Non-Lapasable
Central Pool Resources (NLCPR) Package I
|
Chief Engineer, PHE
Meghalaya,
Shillong |
CE/PHE/TB:92/2009-10/73 Dated : 11.06.12 |
11.06.12 |
Apr-13 |
1435.50 |
Completion Period
12 Months But the LOA was handed over to us at Dec-12 |
3 |
Construction of
Drainage Pumping station (DPS) including ancillary works at point
A-12(Junction of Garland & Bagjola Canal) at Jatragachi, AA-IIE of New
Town Kolkata Project. |
Superintending
Engineer
New Town Kolkata water Supply Circle
Public Health Engineering Directorate
Government of West Bengal
|
Memo No. 626/NTK
(W-178) Dt. 19.06.12 |
16.06.2012 |
Sep-13 |
1078.50 |
Completion Period
15 Months |
4 |
Development and
Operation & Maintenance of Batala - Mehta - Beas Road (MDR-66) on
Design, Build, Finance, Operate and Transfer (DBFOT) basis in the state
of Punjab.
|
Chief Eingineer
(IP)
PB. PWD B&R Branch
SCO 341-42, 2nd Floor,
Sector - 34-A Chandigarh |
IP/CH/5890 Dt.
07.08.2012 |
07.08.2012 |
550 Days |
6800.00 |
|
5 |
Earthwork in
filling, cutting, blanketing, construction of minor bridges, platform
walls/flooring, drains, station buildings, gate lodges, roads etc. and
other ancillary works in between Bandel (incl. yard) and Talandu (incl.
yard up to Km. 51.00) in connection with construction of 3rd line
between Bandel and Bainchi
|
Chief
Engineer/Con/VI
Eastern Railway
14, Strand Road, 4th Floor
Kolkata - 700001 |
CAO/Con/WT/8873
14.08.2012 |
14.08.2012 |
Jan-14 |
4490.52 |
Completion Period
18 Months |
6 |
Construction of
Embankment, Side Drains, Retaining Walls and Blanketing works, Bridges
(Minor and Major) and other Ancillary items for "Constructions of New
Broad Gauge Railway Line from Jogbani to Biratnagar (Nepal)" in Nepal
portion from Km. 5+445 to Km. 18+601
|
General Manager/SR
Ircon International Limited
C-4, District Centre, Saket,
New Delhi - 110017 |
IRCON/CC/TN/JBNRL-2051/EMBANK/12 /650/1134 Dt. 28.09.12 |
28.09.2012 |
Dec-13 |
3817.32 |
Completion Period
15 Months |
7 |
Improvement&
Widening of Aizawl City Roads Phase-I under JnNURM Package -I (Sh:
Strengthening & Improvement of Existing Pavement )
|
Executinv Engineer,
PWD,
Aizawl Road North Division,
Aizawl |
T-11013/43/09/ARN/ JNNURM/116 Dated : 22.11.12 |
22.11.12 |
Nov-14 |
1962.47 |
Completion Period
24 Months |
8 |
Construction of
Water Supply System for Nongstoin Urban Water Supply Scheme (Package -
I)
|
Chief Engineer,
PHE,
Meghalaya, Shillong |
CE/PHE/TB:157/2011-12/Pt/2 |
22.12.12 |
Jun-14 |
2891.45 |
Completion Period
18 Months |
9 |
Construction of
Additional Secretariat Building at Khatla, Aizawl
|
Executive Engineer,
PWD
Project Division No - I,
Aizawl, Mizoram
|
PD-I/11/Tech/2011-2012/54 Dt. 10.01.2013 |
10.01.13 |
Jan-16 |
1710.01 |
Completion Period
36 Months |
10 |
Supplying and Laying
of Distribution Network of 318 Km Length in Kohima Municipal Council
Area. |
Program Director
State Investment Programme Management and Implementation unit
Old Secretariat Complex, Post Box No. 735
Kohima - 797001, Nagaland
|
SIPMIU/TB/WS/T-2/2011-12 Dt. 24.01.13 |
24.01.13 |
Feb-15 |
3227.66 |
Completion Period
730 days |
11 |
Surveying, planning,
designing, delivery, erection, construction, commissioning and
completion in all respect of all Civil, Electrical and Mechanical Works
including all allied, related and enabling works for piped water supply
scheme in Raipur Block of Bankura District with Sub-surface / ground
water as source followed by 06 (six) months of Trial Run and subsequent
Operation & Maintenance for 05(five) years
|
Superintending
Engineer,
Western Circle PHE Dte.
Narampur, PHE Complex
Paschim Medinipur,
Pin - 721101 |
Memo No. 2815/WC
Dated 04.03.13 |
04.03.2013 |
Nov-15 |
7024.18 |
Construction
Completion Period 600 days
(5 years operation & Maintenance)
Construction Amount Rs.55.25Cr and balance amount O & M |
12 |
Construction and
Rehabilitation of Drainage Facilities in Cuttack (Package No.
JICA/OWSSB/OISIP/04) |
Chief Engineer
OISIP JICA,
Odisha Water Supply and Sewerage Board
OWSSB,
Mahanadivihar, Nayabazar,
Cuttack - 753004
|
677/OWSSB Dated
13.03.2013 |
13.03.2013 |
Mar-16 |
65911.00 |
Completion Period 3
years TANTIA - VOLTAS (JV) 70:30 JV |
|
|
|
|
Total -- |
102413.14 |
|