a)

Summary Introduction

To determine: The suitable outsourcing provider using factor- rating method.

Introduction:

Factor-rating method:

The factor-rating method is a quantitative approach to make a decision from various alternatives such that the decision is beneficial to the firm involved. This method is utilized to decide on new layout, new locations, best supplier, outsourcing providers etc.

a)

Expert Solution
Check Mark

Answer to Problem 8P

The suitable outsourcing provider is Canada.

Explanation of Solution

Given information:

Selection criterion Weight England Canada
Price of service from outsourcer 0.1 2 3
Nearness of facilities to client 0.6 3 1
Level of technology 0.2 1 3
History of successful outsourcing 0.1 1 2

Low Risk = 1

High Risk = 3

Formula to calculate weighted risk:

Weighted Risk = Weight × Risk rating

Formula to calculate Total weighted risk:

Total weighted risk = Individualweightedrisk

Principles Of Operations Management, Chapter 2, Problem 8P , additional homework tip  1

Excel Formula:

Principles Of Operations Management, Chapter 2, Problem 8P , additional homework tip  2

Calculation of weighted risk for England:

The weighted risk is calculated my multiplying the weights with risk rating of each criteria.

The weighted risk is calculated as follows:

Service from outsourcer:

Price of service from outsourcer = 0.1 × 2=0.2

The weighted risk for price of service from outsourcer is 0.2.

Nearness of facilities to client:

Nearness of facilities to client = 0.6 × 3=1.8

The weighted risk for Nearness of facilities to client is 1.8.

Level of Technology:

Level of Technology = 0.2 × 1=0.2

The weighted risk for Level of Technology is 0.2.

History of successful outsourcing:

History of successful outsourcing = 0.1 × 1=0.1

The weighted risk for History of successful outsourcing is 0.1.

Calculation of Total weighted risk:

The total weighted risk is calculated be summing all the weighted risk values.

Total weighted risk = 0.2 + 1.8 + 0.2 + 0.1= 2.3

The total weighted risk for England is 2.3.

Calculation of weighted risk for Canada:

The weighted risk is calculated my multiplying the weights with risk rating of each criteria.

The weighted risk is calculated as follows:

Price of service from outsourcer:

Price of service from outsourcer = 0.1 × 3=0.3

The weighted risk for price of service from outsourcer is 0.3.

Nearness of facilities to client:

Nearness of facilities to client = 0.6 × 1=0.6

The weighted risk for nearness of facilities to client is 0.6.

Level of Technology:

Level of Technology = 0.2 × 3=0.6

The weighted risk for Level of Technology is 0.6.

History of successful outsourcing:

History of successful outsourcing = 0.1 × 2=0.2

The weighted risk for History of successful outsourcing is 0.2.

Calculation of Total weighted risk:

The total weighted risk is calculated be summing all the weighted risk values.

Total weighted risk = 0.3 + 0.6 + 0.6 + 0.2= 1.7

The total weighted risk for Canada is 1.7.

The weighted risk value for England is 2.3. The weighted risk value for Canada is 1.7. Since, the risk value for Canada is less for England (1.7 < 2.3), Canada is selected.

The suitable outsourcing provider is Canada.

b)

Summary Introduction

To determine: The impact of doubling the weights used in part (a).

Introduction:

Factor-rating method:

The factor-rating method is a quantitative approach to make a decision from various alternatives such that the decision is beneficial to the firm involved. This method is utilized to decide on new layout, new locations, best supplier, outsourcing providers etc.

b)

Expert Solution
Check Mark

Answer to Problem 8P

The Doubling of weights will have No Change.

Explanation of Solution

Given information:

Selection criterion Weight England Canada
Price of service from outsourcer 0.2 2 3
Nearness of facilities to client 1.2 3 1
Level of technology 0.4 1 3
History of successful outsourcing 0.2 1 2

Low Risk = 1

High Risk = 3

Formula to calculate weighted risk:

Weighted Risk = Weight × Risk rating

Formula to calculate Total weighted risk:

Total weighted risk = Individualweightedrisk

Principles Of Operations Management, Chapter 2, Problem 8P , additional homework tip  3

Excel Formula:

Principles Of Operations Management, Chapter 2, Problem 8P , additional homework tip  4

Calculation of weighted risk for England:

The weighted risk is calculated my multiplying the weights with risk rating of each criteria.

The weighted risk is calculated as follows:

Price of service from outsourcer:

Price of service from outsourcer = 0.2 × 2=0.4

The weighted risk for price of service from outsourcer is 0.4.

Nearness of facilities to client:

Nearness of facilities to client = 1.2 × 3=3.6

The weighted risk for nearness of facilities to client is 3.6.

Level of Technology:

Level of Technology = 0.4 × 1=0.4

The weighted risk for Level of Technology is 0.4.

History of successful outsourcing:

History of successful outsourcing = 0.2 × 1=0.2

The weighted risk for History of successful outsourcing is 0.2.

Calculation of Total weighted risk:

The total weighted risk is calculated be summing all the weighted risk values.

Total weighted risk = 0.4 + 3.6 + 0.4 + 0.2= 4.6

The total weighted risk for England is 4.6.

Calculation of weighted risk for Canada:

The weighted risk is calculated my multiplying the weights with risk rating of each criteria.

The weighted risk is calculated as follows:

Price of service from outsourcer:

Price of service from outsourcer = 0.2 × 3=0.6

The weighted risk for price of service from outsourcer is 0.6.

Nearness of facilities to client:

Nearness of facilities to client = 1.2 × 1= 1.2

The weighted risk for nearness of facilities to client is 1.2.

Level of Technology:

Level of Technology = 0.4 × 3=1.2

The weighted risk for Level of Technology is 1.2.

History of successful outsourcing:

History of successful outsourcing = 0.2 × 2=0.4

The weighted risk for History of successful outsourcing is 0.4.

Calculation of Total weighted risk:

The total weighted risk is calculated be summing all the weighted risk values.

Total weighted risk = 0.6 + 1.2 + 1.2 + 0.4= 3.4

The total weighted risk for Canada is 3.4.

The weighted risk value for England is 4.6. The weighted risk value for Canada is 3.4. Since, the risk value for Canada is less for England (3.4 < 4.6), Canada is selected.

The doubling of weights of the risk avoidance criteria does not alter the result arrived at in part (a). The weighted risk value is doubled for England and Canada. But, the risk value of Canada is still lower than England. The result will not change irrespective of doubling the weights because the risk avoidance criterion value is unaltered.

Hence, the Doubling of weights will have No Change.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
1. Strategic Predispositions of MNEsChapter 8 outlines four strategic predispositions—ethnocentric, polycentric, regiocentric, and geocentric. a. Define each orientation and explain how it shapes an MNE’s approach to market entry, integration, and control. b. Provide a real or hypothetical example of a firm (e.g., IKEA, Samsung) for each orientation, justifying why that orientation fits based on its structure and policies. c. Evaluate the potential benefits and downsides of each orientation for international competitiveness and global performance. 2. External and Internal Analysis in Strategy FormulationChapter 8 emphasizes the importance of external environmental assessment (macro and industry-level forces) and internal resource evaluation when crafting a multinational strategy. a. Describe key elements of external assessment (e.g., market size, political risk, competition) and internal evaluation (e.g., firm capabilities, value-chain strengths). b. Choose an MNE (real or…
1. Structural Arrangements for Global Integration vs Local ResponsivenessChapter 9 explains how MNEs structure their organizations to balance global efficiency and local responsiveness. a. Describe the main organizational structures covered (e.g., international division, global product division, geographic/regional division, matrix, transnational). b. Choose one global MNE (real or hypothetical) and argue which structure (or hybrid) best suits its strategy—taking into account industry, scale, and diversity of markets. c. Discuss two key challenges this MNE might face under that structure (e.g., coordination complexity, role ambiguity), and recommend how to address them. 2. Control Mechanisms & Coordination in MNEsEffective international organization also relies on control systems and coordination processes. a. Define and contrast different control mechanisms (e.g., output controls, process controls, cultural/values-based controls) as presented in the chapter. b. Provide…
3. Overcoming Negotiation Challenges:Describe two common challenges negotiators face during the planning phase. How can these challenges be anticipated and effectively addressed? 4. Strategic Planning in Practice:Think of a past negotiation experience (real or hypothetical). How would applying the principles of strategic negotiation planning from this chapter have improved the outcome? 5. Chapter Summary Reflection:Summarize the major insights from Chapter 4. How does strategic planning enhance a negotiator’s ability to stay focused and adaptable during complex negotiations?
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Purchasing and Supply Chain Management
    Operations Management
    ISBN:9781285869681
    Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
    Publisher:Cengage Learning
    Text book image
    MARKETING 2018
    Marketing
    ISBN:9780357033753
    Author:Pride
    Publisher:CENGAGE L
    Text book image
    Contemporary Marketing
    Marketing
    ISBN:9780357033777
    Author:Louis E. Boone, David L. Kurtz
    Publisher:Cengage Learning
  • Text book image
    Practical Management Science
    Operations Management
    ISBN:9781337406659
    Author:WINSTON, Wayne L.
    Publisher:Cengage,
    Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Contemporary Marketing
Marketing
ISBN:9780357033777
Author:Louis E. Boone, David L. Kurtz
Publisher:Cengage Learning
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing