
Concept explainers
(a)
Find the addition of matrix
(a)

Answer to Problem 17P
The addition of matrix
Explanation of Solution
Given data:
Calculation:
Add two matrixes
Reduce the equation (1) as follows,
Therefore, the addition of matrix
Conclusion:
Thus, the addition of matrix
(b)
Find the subtraction of matrix
(b)

Answer to Problem 17P
The subtraction of matrix
Explanation of Solution
Given data:
Calculation:
Subtract two matrixes
Reduce the equation (2) as follows,
Therefore, the subtraction of matrix
Conclusion:
Thus, the subtraction of matrix
(c)
Find the value of
(c)

Answer to Problem 17P
The value of
Explanation of Solution
Given data:
Calculation:
Three times of matrix
Reduce equation (3) as follows,
Therefore, the value of
Conclusion:
Thus, the value of
(d)
Find the multiplication of matrix
(d)

Answer to Problem 17P
The multiplication of matrix
Explanation of Solution
Given data:
Calculation:
Multiply the matrix
Reduce equation (4) as follows,
Therefore, the multiplication of matrix
Conclusion:
Therefore, the multiplication of matrix
(e)
Find the multiplication of matrix
(e)

Answer to Problem 17P
The multiplication of matrix
Explanation of Solution
Given data:
Calculation:
Multiply the matrix
Reduce equation (5) as follows,
Therefore, the multiplication of matrix
Conclusion:
Therefore, the multiplication of matrix
(f)
Find the square of matrix
(f)

Answer to Problem 17P
The square of matrix
Explanation of Solution
Given data:
Calculation:
Square of the matrix
Reduce equation (6) as follows,
Therefore, the square of matrix
Conclusion:
Therefore, the square of matrix
(g)
Prove the operation
(g)

Explanation of Solution
Given data:
Calculation:
Therefore,
Reduce equation (7) as follows,
Now,
Reduce equation (9) as follows,
Comparing equation (9) and (10),
Hence proved
Conclusion:
Thus, the operation
Want to see more full solutions like this?
Chapter 18 Solutions
LMS Integrated for MindTap Engineering, 2 terms (12 months) Printed Access Card for Moavni's Engineering Fundamentals: An Introduction to Engineering, 5th
- You are viewing Attempt 1/Continue Work * Incorrect The 123-kg industrial door with mass center at G is being positioned for repair by insertion of the 8° wedge under corner B. Horizontal movement is prevented by the small ledge at corner A. If the coefficients of static friction at both the top and bottom wedge surfaces are 0.65, determine the force P required to lift the door at B. Assume a = 1.4 m, b = 1.2 m, a = 8° A Answer: P = 1144.28 N Barrow_forwardHow can new sustainable materials change dead load calculations in future designs in earthquake-prone areas?arrow_forwardGiven the truss with loading shown. Note that the roller connection at Joint D is in atrack so that it cannot move in the x-direction, but it can roll in the y-direction.Solve the truss with the virtual load you would use if you are going to solve for the verticaldeflection at Joint E using the method of virtual work.Note: Just solve the truss. You DO NOT need to find the vertical deflection at Joint E.arrow_forward
- Question (1): (18 Marks) Gaza City has a total population of 650,000 inhabitant, where 75% of the population is connected to wastewater collection system. The water consumption per capita is 100 L/day. Currently, the collected flow treated partially by aerated lagoon system. The municipality intend to change the treatment system to a completely mixed activated sludge system to be used for organic matter removal only to fulfill the Palestinian standards for reuse (Soluble BOD 30 mg/l). The given data from the municipality laboratory and assumptions: ⚫ The influent soluble Biological Oxygen demand = 500 mg/l. Biomass yield (Y) = 0.5 mg VSS/mg BOD removed • Endogenous decay rate constant (Ka) = 0.05d¹ • • The concentration of biomass (X) = 3000 mg MLVSS The concentration of recycled biomass (X) = 10000 mg MLVSS/L Growth rate (d) 2.5 1.25 100 For the completely mixed activated sludge system find the following: a) The average flow to the treatment plant. b) The mean cell residence time. c)…arrow_forwardQuestion (3): (20 Marks) You have been assigned to design a secondary wastewater treatment component based on a tricking filter technique. The flow rate is 3500 m³/day, the raw wastewater has a BOD5 of 600 mg/l. This wastewater is primarily treated with an efficiency of 35%. • Assume suitable design criteria to obtain a BOD effluent of 15 mg/l. Design the secondary clarifier • Perform all the necessary cheeks on your design.arrow_forwardQuestion (3): (20 Marks) You have been assigned to design a secondary wastewater treatment component based on a tricking filter technique. The flow rate is 3500 m³/day, the raw wastewater has a BOD5 of 600 mg/l. This wastewater is primarily treated with an efficiency of 35%. • Assume suitable design criteria to obtain a BOD effluent of 15 mg/l. Design the secondary clarifier • Perform all the necessary cheeks on your design.arrow_forward
- Data:Total budget = $25,000BCWS = $ 8,333BCWP = $ 6,400ACWP = $ 7,800Project duration = 40 daysData date: 10 days Perform the following analyses of the project based on the data given above.a. Cost Variance b. Schedule Variancearrow_forwardPlease explain why large initial separations on the EV S-Curve between the lines for ACWPand BCWP with BCWP above the ACWP may be an indicator of excessive front loading.arrow_forwardData:Total budget = $25,000BCWS = $ 8,333BCWP = $ 6,400ACWP = $ 7,800Project duration = 40 daysData date: 10 days Plot an S-Curve and show Cost Variance and Schedule Variance on it.arrow_forward
- Water table A L₁ = 2 m Sand y = 15.9 kN/m³ c' = 0 $' = 32° E L₂ = 3 m D Determine: a) Theoretical Depth and actual depth of penetration Sand Ysat 19.33 kN/m³ c' = 0 $' = 32° Clay c = 47 kN/m² =0arrow_forward3. The following Sheet Pile is to be designed for a granular soil without the influence of the water table: Determine: L = 5m Y = 15.9kN/m³ $' = 32° Gall = 172MN/m² e) Theoretical Embedment Deptharrow_forward3. The following Sheet Pile is to be designed for a granular soil without the influence of the water table: Determine: L = 5m y = 15.9kN/m³ $'=32° Gall = 172MN/m² f) Actual Embedment depth taking into account a 30% increasearrow_forward
- Engineering Fundamentals: An Introduction to Engi...Civil EngineeringISBN:9781305084766Author:Saeed MoaveniPublisher:Cengage LearningFundamentals Of Construction EstimatingCivil EngineeringISBN:9781337399395Author:Pratt, David J.Publisher:Cengage,

