Published Results (2):

Hardware Vendor
Test Sponsor
System
Enclosure (if applicable)
Nodes JVM Vendor Processor Total
Memory (GB)
Submeasurements Result
(Overall ssj_ops/watt)
CPU Description MHz Chips Cores Total
Threads
ssj_ops
@ 100%
avg. watts
@ 100%
avg. watts
@ active idle
Huawei Technologies Co., Ltd FusionServer CH121 V3
Huawei FusionServer E9000
Dec 21, 2016 | HTML | Text
8 Oracle Corporation Intel Xeon E5-2683 V4 2100 16 256 512 4096 24,662,648 3,868 1,080 5,316
Huawei Technologies Co., Ltd FusionServer CH121 V3
Huawei FusionServer E9000
Dec 21, 2016 | HTML | Text
10 Oracle Corporation Intel Xeon E5-2683 V4 2100 20 320 640 5120 30,620,865 4,425 1,250 5,555