Student center construction to require April 22 water shutoff in some campus buildings
Work on the new W.R. Davies Student Center construction project will require water to be shut off for approximately four hours starting at 3 p.m. April 22 in several lower-campus buildings at UW-Eau Claire. More information.
Monday, April 18, 2011
Foundation installation to begin on student center construction project
On Feb. 18, workers will begin installing the foundation of the approximately 170,000-square-foot W.R. Davies Student Center at UW-Eau Claire. More information.
Tuesday, March 29, 2011
April 3 power outage to affect lower campus, McPhee/Olson Addition
An eight- to 10-hour electrical outage is planned for April 3 in buildings south and east of the Chippewa River on the University of Wisconsin-Eau Claire lower campus and in the McPhee Physical Education Center and Ade Olson Addition on upper campus. The outage will begin at 7 a.m. More information.
Friday, March 18, 2011
Noise and vibration alert: Geopiers installation to begin March 28
Installation of approximately 700 Geopiers that will support the foundation of the new UW-Eau Claire student center will begin March 28. There will be noise and vibrations associated with this phase of the project. More information.
Wednesday, March 16, 2011
UW-Eau Claire education building among capital budget items approved by State Building Commission
The State Building Commission approves Governor Scott Walker’s 2011-13 capital budget recommendations, which include $44 million for a new education building at UW-Eau Claire. Read UW System news release.
Tuesday, March 15, 2011
UW-Eau Claire education building included in Gov. Walker's 2011-13 capital budget
Gov. Scott Walker has released his proposed 2011-13 capital budget, which includes $44 million for an education building at UW-Eau Claire. Read Governor's Office news release, complete list of capital budget recommendations.
Student center construction site photos
This was the view March 8 from Phillips Science Hall of UW-Eau Claire's student center construction site. See more photos on UW-Eau Claire's Facebook page. (UW-Eau Claire photo by Bill Hoepner)